Everything is progressing well! The sheathing of the exterior is well under way, the framework of the soffits is being blocked out, ductwork is being installed, and the crews have begun to lay in the cabling.

Advertisements

Read Full Post »

We are now in the 27th week of construction and things are going well! The steel structure of the dramatic entryway is nearly complete, the exterior metal stud installation is progressing well, and exterior sheathing is beginning to go up. The roofing deck installation is complete and ready for roofing installation to begin.

This slideshow requires JavaScript.

Read Full Post »

Exterior metal stud framing installation is in progress.

Framing of the front entrance in progress.

Columns for masonry fins have been installed.