Things are progressing well!

Fire Hydrant Installed

 

Asphalt On The Driveways

Building Pad Ready

Foundation and Retaining Wall Work Has Begun

 

Advertisements

Read Full Post »

The inspections have gone well and the building permit has been issued to commence with the next phase of construction! All storm water detention structures are in place and functioning, and the site has been connected to the water main. The main driveway is being prepared for asphalt, and curbs around the parking areas are being laid out.

 